PBV Environmental Review Requirements Before Construction or Rehabilitation

 PBV Environmental Review: When Clearance Is Required Before Development

A PBV environmental review can determine whether a Project-Based Voucher development is allowed to move from project selection into agreements, acquisition, construction, rehabilitation or other actions that could commit the site. When a Federal environmental review is required, HUD's current PBV rule restricts those actions until the responsible entity or HUD completes the applicable process and the project receives environmental clearance.

There is now an important exception for certain existing housing. Since HOTMA changed the rule, an existing-housing project selected under the PBV site-selection standards effective on or after June 6, 2024 generally does not need an environmental review before the PHA enters the HAP contract solely because it will receive PBV Housing Assistance Payments. New construction and rehabilitation remain a different matter.


Affordable housing development site undergoing environmental review before construction

First Determine Whether an Environmental Review Is Required

HUD environmental regulations at 24 CFR Parts 50 and 58 apply to PBV activities unless the current PBV regulation provides an exception.

The housing type and project history therefore matter at the beginning of the analysis. A project that appears to be an ordinary apartment building may fall into one of three different PBV categories: existing housing, newly constructed housing or rehabilitated housing.

Those categories have different development consequences. The distinction among existing, new-construction and rehabilitated PBV units should be established before anyone assumes which environmental-review sequence applies.

Existing Housing Received a Major HOTMA Exception

For an existing-housing project or proposal selected under the site-selection standards in effect on or after June 6, 2024, § 983.56 states that no environmental review has to be undertaken before entering into the PBV HAP contract solely for PBV Housing Assistance Payments.

The exception has limits.

A Federal environmental review may still be required when another law or regulation requires one because the project is receiving funding other than PBV Housing Assistance Payments.

The exception also depends on when the project or proposal was selected and which version of the PBV site-selection standards governed that selection. A project selected under the older standards does not become exempt merely because its HAP contract will be executed after June 6, 2024.

No PBV Environmental Review Does Not Mean No Site Review

The existing-housing exception is easy to misunderstand.

Even where § 983.56 does not require a Federal environmental review before HAP execution, the PHA still has to make the applicable PBV site and neighborhood determination.

Under § 983.55, the PHA cannot select a PBV site unless the site and neighborhood are reasonably free from conditions that threaten residents' health, safety or general welfare. The current regulation specifically identifies conditions such as contamination, flooding, poor drainage, sewage hazards, abnormal air pollution, excessive noise or vibration, heavy traffic, instability and fire hazards.

That is a PBV site-selection determination. It should not be confused with completing a Federal environmental review under Part 50 or Part 58.

New Construction and Rehabilitation Stay in the Environmental-Review Framework

PBV development activity must comply with the applicable environmental-review requirements in § 983.56.

That applies to newly constructed and rehabilitated PBV housing even though HOTMA gave PHAs more flexibility in other parts of the development process.

For example, current rules can sometimes allow development to begin without a traditional pre-development Agreement when the PHA's Administrative Plan authorizes the applicable flexibility. That flexibility does not erase environmental restrictions.

The PBV AHAP and development rules have to be read together with the environmental-review requirements. A PHA cannot use contract flexibility to bypass a clearance that Federal environmental rules require.

Project Selection Can Occur Before Environmental Clearance

A PHA does not necessarily have to wait for the entire environmental review before selecting the project.

If a required environmental review has not been completed by the proposal or project selection date, however, the PHA's written selection notice has to make the project's status clear.

The notice must state that selection is subject to completion of a favorable environmental review and that the project may be rejected based on the results.

Selection at that point is therefore conditional. It is not environmental approval and does not authorize the owner or PHA to proceed with actions that the environmental restrictions prohibit.

Who Performs the PBV Environmental Review?

Under the normal Part 58 structure, the environmental review is performed by the governmental entity that assumes HUD's environmental responsibilities for the project.

The PBV regulation identifies the responsible entity, or RE, as the unit of general local government with land-use responsibility where the project is located, the county or the State, as applicable.

The responsible entity performs the Federal environmental review under the National Environmental Policy Act and the related Federal laws and authorities incorporated into Part 58.

The PHA does not simply substitute its own project-development review for that Federal determination.

HUD Can Perform the Review in Certain Cases

Not every PBV environmental review is performed under Part 58.

If the PHA objects in writing to the responsible entity performing the environmental review, or the responsible entity declines to perform it, HUD may conduct the review itself.

HUD then performs the review under 24 CFR Part 50.

This creates two possible Federal review paths:

  • A responsible entity performs the review under Part 58.
  • HUD performs the review under Part 50 when the applicable conditions are met.

The project file should make clear which path applies rather than assuming that any local environmental document serves as HUD environmental clearance.

The PHA Still Has an Information Duty

Having a responsible entity or HUD perform the environmental review does not make the PHA passive.

Section 983.56 requires the PHA to supply all available relevant information necessary for the responsible entity, or HUD when applicable, to perform the review.

Project-specific material may involve the property, development scope, proposed activities, prior uses, site conditions and other facts needed to determine which environmental requirements apply.

An owner may therefore be asked to provide information through the PHA even though the owner is not the Federal decision-maker issuing environmental clearance.

Choice-Limiting Actions Must Wait

The most consequential PBV environmental rule concerns what happens while a required review is still pending.

Before the project reaches the required environmental clearance, § 983.56 prohibits the PHA from executing an Agreement or HAP contract with the owner.

The restriction goes further than contract signing.

The PHA, owner and their contractors may not undertake the specified actions involving the property or commit or spend program or local funds for those activities before the applicable environmental condition has been satisfied.

The prohibited activities listed in the PBV regulation include:

  • Acquisition.
  • Rehabilitation.
  • Conversion.
  • Leasing.
  • Repair.
  • Disposition.
  • Demolition.
  • Construction.

These restrictions protect the environmental review from becoming a paperwork exercise performed after the project has already been irreversibly committed.

Private or Local Money Does Not Necessarily Solve the Timing Problem

A common mistake is to assume that work can safely start before environmental clearance as long as HUD money is not paying for that particular activity.

That is not the general rule.

Section 983.56 expressly restricts the PHA, owner and contractors from the listed property actions and from committing or spending program or local funds for them while the required review is pending.

Part 58 also restricts participants from committing non-HUD funds when the action would have an adverse environmental impact or limit reasonable alternatives before the applicable release-of-funds approval.

The source of the construction check is therefore not the only issue. The question is whether the proposed action would prematurely commit the project or limit the environmental decision-maker's reasonable alternatives.

Environmental Clearance Can Be Reached in Three Different Ways

Section 983.56 identifies the conditions that allow the PBV project to move beyond the environmental restriction.

One route applies when the responsible entity determines that the activity is exempt under the applicable Part 58 provision or is categorically excluded and not subject to compliance with the related environmental laws. The responsible entity must make and document that determination.

For a Part 58 review that requires release of funds, the responsible entity completes the required environmental-review procedures and submits the Request for Release of Funds and Certification, form HUD-7015.15. HUD then approves the request by issuing a Letter to Proceed or form HUD-7015.16.

Where HUD performs the environmental review under Part 50, the restriction ends when HUD has completed its review and notified the PHA in writing that environmental clearance has been provided.

The project record should identify which of these routes actually cleared the project.

Do Not Treat the RROF as the Final Clearance

For a Part 58 project requiring a Request for Release of Funds, submitting form HUD-7015.15 is not the final authorization by itself.

The PBV regulation requires HUD approval of the request. HUD provides that authorization through a Letter to Proceed or form HUD-7015.16.

That distinction matters when a development team is deciding whether a restricted action may begin. A copy of a submitted request does not show that HUD has released the project to proceed.

Starting Too Early Can Jeopardize Environmental Clearance

The consequence for premature action is unusually direct.

When an environmental review is required, § 983.56 states that HUD will not issue the Letter to Proceed, form HUD-7015.16 or environmental clearance if the PHA, owner or contractors have already undertaken one of the restricted activities identified in the regulation.

That makes the timing rule much more than an administrative preference.

An owner should not assume the issue can simply be repaired later by submitting an environmental report after construction, acquisition, demolition or another restricted action has already occurred.

Before taking an action that could commit the project, the safer project-management question is whether the required Federal environmental clearance has actually been documented.

Contamination Can Matter at Both the Site-Selection and Federal Review Stages

Environmental contamination illustrates why PBV site review and Federal environmental review should not be merged into one concept.

At the PBV site-selection stage, § 983.55 requires the PHA to consider serious adverse environmental conditions that could affect residents' health or safety, expressly including contamination.

Where a Federal environmental review is required, HUD environmental standards under Parts 50 and 58 can require a more formal examination of hazardous materials, toxic chemicals, gases, radioactive substances and evidence of contamination on or near the property.

For covered multifamily reviews, prior uses of the site and nearby evidence of contamination may become relevant. Sites near former industrial uses, landfills, dumps or other potential sources of hazardous material can require further examination under the applicable Federal environmental process.

The appropriate environmental reviewer determines what investigation or documentation is necessary. A PBV proposal should not declare a site environmentally clear based only on the absence of visible contamination.

Historic Properties May Trigger a Separate Federal Review Issue

Environmental review under Parts 50 and 58 covers more than contamination and physical environmental hazards.

Related Federal laws can require consideration of historic properties under the National Historic Preservation Act and its Section 106 process.

That can become relevant when rehabilitation, demolition, construction or another project action could affect a historic property or historic district.

The fact that the building is physically safe for PBV occupancy does not resolve a historic-preservation review. Those are different Federal questions.

Floodplains, Wetlands, Noise and Other Authorities May Also Apply

The exact environmental issues depend on the site and the proposed activity.

HUD's environmental framework includes requirements that can involve floodplain and wetland protection, endangered species, air quality, noise, explosive or flammable hazards and other Federal environmental laws or standards.

Not every PBV project requires the same analysis of every subject. The responsible entity or HUD determines the applicable level and scope of review based on the project.

That is why copying an environmental checklist from another development is not a reliable substitute for the review of the actual PBV site and activity.

Mitigation Measures Become Part of the Project's Compliance Record

An environmental review does not always end with an unconditional yes or no.

The review may establish mitigating measures or other conditions that have to be satisfied for the project to proceed.

Section 983.56 requires the PHA to document those measures or conditions and either complete them or require the owner to carry them out.

The PHA therefore cannot treat environmental clearance as complete while ignoring conditions that were part of the determination.

The project file should preserve both the clearance and the mitigation requirements tied to it.

What Should the PBV Environmental File Show?

A well-documented project should allow a reviewer to identify the environmental status without reconstructing it from scattered correspondence.

Depending on the path that applies, the record may include:

  • The project's PBV housing classification and selection date.
  • Evidence establishing whether the existing-housing HOTMA exception applies.
  • The responsible entity or HUD identification.
  • The documented exempt or categorically excluded determination when applicable.
  • The Federal environmental review record required for the project.
  • Form HUD-7015.15 when a Request for Release of Funds is required.
  • The HUD Letter to Proceed or form HUD-7015.16.
  • Written HUD Part 50 clearance when HUD performs the review.
  • Environmental conditions or mitigation measures.
  • Records showing completion of required mitigation.
  • Relevant information supplied by the PHA or owner for the review.

The exact file will differ by project. What should not be ambiguous is whether a review was required, who performed it, and what document authorized the project to move forward.

Environmental Review Is Not the PBV Physical Inspection

A Federal environmental review and a PBV unit inspection serve different purposes.

The environmental process evaluates the proposed project and site under NEPA, HUD environmental regulations and related Federal environmental authorities when those requirements apply.

A PBV physical inspection determines whether units satisfy the applicable housing-quality requirements for assistance.

Passing an inspection does not provide environmental clearance. Environmental clearance likewise does not establish that a completed unit passes its required PBV inspection.

A development project may need both before reaching the appropriate stage of PBV assistance.

Check Environmental Status Before Committing the Site

For an existing PBV project, first determine whether the June 6, 2024 HOTMA exception applies and whether another Federal funding source independently requires an environmental review.

For new construction or rehabilitation, determine who is performing the required review and whether the project has reached the applicable exempt determination, HUD-approved release of funds or written Part 50 clearance before taking a restricted action.

Project selection alone is not that clearance. An AHAP alone is not that clearance. A submitted environmental document is not necessarily that clearance.

The controlling evidence is the environmental determination and authorization required by the review path that actually applies to the project.

Comments